When should you order stock before Lunar New Year 2027?

Lunar New Year 2027 is Saturday 6 February and China's Spring Festival holiday runs from 5 to 13 February. When factories close, when to confirm orders and book freight, and a dated plan for stock you need from February to April.

3 min readPublished

Drawing of one listing joined to marketplace tabs
On this page

Lunar New Year 2027 is Saturday 6 February. China's State Council has set the Spring Festival holiday from Friday 5 February to Saturday 13 February, nine days, with Sunday 31 January and Sunday 14 February as make-up working days. If you buy stock from Chinese factories, that is the date your February to April stock depends on.

This Guide says when factories close, when to confirm orders and book freight, and gives a dated plan.

When is Lunar New Year 2027, and when do Chinese factories close?

Lunar New Year 2027 is Saturday 6 February. The Spring Festival holiday runs from 5 to 13 February.

Factories close for longer than the official holiday. Flexport, the freight forwarder, says factories are closed or working at reduced capacity for at least 4 weeks around the new year. Most factory workers travel a long way home for the holiday, so Flexport warns of closings, delays and disruption in the weeks before and after it.

Ordering before the factories close: an example plan

An example of the order dates to work back from the holiday that starts 5 February.

  • Your example date
  • Holiday
  • Lunar New Year
  1. Example: confirm the reorderAsk for the supplier's closing and reopening dates and a cargo ready date in writing.
  2. Example: book ocean freightFour weeks before the holiday, and add one to two weeks to your transit plan.
  3. Spring Festival holiday startsA fault found now waits until the factory reopens.
  4. Lunar New YearSaturday.
  5. Spring Festival holiday endsFactories restart slowly.

When should you place orders before Lunar New Year 2027?

Order everything you need from February to April before the slowdown, and book the freight early. Lead time is the time from placing an order to the stock arriving, and it grows around the holiday. Work through it in this order:

  1. Count the weeks you must cover, from early February to the middle of March, for every product you sell.
  2. Confirm purchase orders in December, your written orders to suppliers. Ask each supplier for its closing and reopening dates, and a cargo ready date in writing, the day your goods are packed and ready for pickup.
  3. Book ocean freight 3 to 4 weeks before the holiday, which for 2027 means by mid-January at the latest.
  4. Add one to two weeks to your transit plan, because ships and containers are tight before the holiday.
  5. Inspect before the factory closes. A fault found after 5 February waits until the factory reopens.
  6. Plan a faster route for gaps. Use air freight or a premium shared-container service for stock that cannot wait, booked early because that space is tight too.

If you sell yoga mats and run out in late February, confirm the reorder on 15 December. Book ocean freight on 8 January, four weeks before the holiday starts on 5 February, and add two weeks to the expected transit time when you promise stock on your listings.

What should you do this week?

  1. Write down the weeks of stock you need from February to April, product by product.
  2. Email each supplier for its closing and reopening dates.
  3. Choose the day you will confirm each purchase order, in December.
  4. Note mid-January as the latest day to book ocean freight.

Stock you order costs money to hold: our Guides to Amazon FBA storage fees and Walmart WFS storage fees give the rates. Our plan for Q5 to March has the rest of the quarter.

Your questions, answered

When is Lunar New Year 2027?

Lunar New Year 2027 is Saturday 6 February, and China's official Spring Festival holiday runs from 5 to 13 February 2027.

How long do Chinese factories close for Lunar New Year?

Flexport says factories are closed or working at reduced capacity for at least 4 weeks around the new year.

When should I book freight before Chinese New Year 2027?

Book ocean freight at least 3 to 4 weeks before the holiday, which starts on 5 February 2027.

How much longer does shipping take around Lunar New Year?

Add one to two weeks to your transit plan.

Which days are working days to make up for the holiday?

Sunday 31 January and Sunday 14 February 2027.